Glossary

Construction terms, plainly defined

Clear definitions of the construction, estimating, and building-code terms contractors and homeowners run into — each one short, accurate, and linked to where it matters.

AFCI (arc-fault circuit interrupter)

An arc-fault circuit interrupter (AFCI) is a protective device that detects dangerous electrical arcing and shuts off the circuit to prevent fires.

GFCI (ground-fault circuit interrupter)

A ground-fault circuit interrupter (GFCI) is a device that cuts power within milliseconds when it detects current leaking to ground, protecting people from electric shock.

Egress / EERO (emergency escape and rescue opening)

An emergency escape and rescue opening (EERO) is a window or door large enough to escape through and for a firefighter to enter — required in every sleeping room.

AHJ (authority having jurisdiction)

The authority having jurisdiction (AHJ) is the local agency or official — usually the building department — that adopts, interprets, and enforces the code where you build.

Takeoff (quantity takeoff)

A takeoff is the process of measuring and counting the materials and quantities needed for a project directly from the drawings — the basis of an estimate.

Overhead and profit (O&P)

Overhead and profit (O&P) is the markup added to the direct cost of a job to cover a contractor's business costs (overhead) and earnings (profit).

Basis of estimate (BOE)

A basis of estimate (BOE) is the documented set of assumptions, inclusions, exclusions, and data sources behind an estimate — the 'show your work' for a number.

AACE estimate class

AACE estimate classes (Class 5 to Class 1) describe how mature and accurate an estimate is, based on how complete the project's design is.

RFI (request for information)

A request for information (RFI) is a formal question from the contractor to the design team to clarify or resolve something unclear in the drawings or specifications.

Submittal

A submittal is the documentation a contractor provides — product data, shop drawings, samples — for the design team to review against the specifications before installation.

Change order

A change order is a written, signed agreement that modifies the contract's scope, price, or schedule after work has begun.

Punch list

A punch list is the list of remaining or deficient items a contractor must complete or correct before a project is considered finished.

CPM schedule (critical path method)

A critical path method (CPM) schedule is a project timeline that maps task dependencies to compute the longest chain of work — the 'critical path' that drives the finish date.

Earned value management (EVM)

Earned value management (EVM) is a method that combines scope, schedule, and cost to measure whether a project is ahead or behind and over or under budget — with objective indices.

Lien waiver

A lien waiver is a signed document in which a contractor, subcontractor, or supplier gives up their right to file a mechanic's lien for payment they have received.

Pay application (pay app / draw)

A pay application (or 'draw') is a contractor's formal request for a progress payment, showing the work completed to date against the schedule of values.

R-value

R-value measures how well insulation resists heat flow — the higher the R-value, the better the insulating performance.

Load-bearing wall

A load-bearing wall is a wall that carries structural weight from above — floors, the roof, or other walls — down to the foundation.

Setback (zoning)

A setback is the minimum distance a building must be kept from property lines, streets, or other features, set by local zoning rules.

Certificate of occupancy (CO)

A certificate of occupancy (CO) is the document a building department issues confirming a structure complies with code and is safe to occupy for its intended use.

Browse the code library →